Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201716—Rev 13
71
Distributed Bypass Installation Checklist
o
Each cabinet in the distributed bypass system is placed in its installed location.
o
All conduits and cables are properly routed to the UPS cabinets and to the tie cabinet or distribution panel.
o
All power cables are properly sized and terminated.
o
A ground conductor is properly installed.
o
Controller Area Network (CAN) wiring between the UPS cabinets is properly installed.
o
Pull-chain wiring between the UPS cabinets is properly installed.
o
Adequate workspace exists around the UPS cabinets, the tie cabinet, and other cabinets.
o
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.