84
Eaton
®
Power Xpert
®
9395P-900 Installation and Operation Manual 164000501—Rev 12
9.
Using hardware from the external wiring terminal hardware kit (see
), connect phase A, B, and C
wiring from the output terminals of each UPS unit to the customer-supplied tie cabinet or load distribution
panel. See paragraph
UPS System Power Wiring Preparation
for wiring and termination
requirements.
10. Proceed to paragraph
11. Using hardware from the external wiring terminal hardware kit (see ), connect phase A, B, and C power
wiring from output terminals to the critical load. See paragraph
UPS System Power Wiring Preparation
for wiring and termination requirements.
12. Proceed to paragraph
Figure 40. ISBM Section Power Terminal Locations
NOTE