Eaton
®
Power Xpert
®
9395P-900 Installation and Operation Manual 164000501—Rev 12
35
Figure 21. Remote EPO Switch Dimensions
Dimensions are in millimeters [inches].
Front View
remove key
1/2” Knockout Pattern
(Typical 5 Sides)
115.8
[4.56]
114.3
[4.50]
0.87
[0.22]
88.9
[3.50]
1.57
[0.40]
Needed to
95.3
[3.57]
(Square)
33..22..44
U
UP
PS
S S
Syysstteem
m P
Poow
weerr W
Wiirriinngg P
Prreeppaarraattiioonn
Refer to national and local electrical codes for acceptable external wiring practices.
•
To allow for future kVA upgrades, consider installing a derated UPS using wiring and external overcurrent
protection breakers sized for a fully rated UPS.
•
To allow for a future upgrade, install a three UPM model using conductors and external overcurrent
protection breakers sized the same as a fully rated 900 kVA model.
•
For external wiring, use 75°C copper or aluminum wire. Wire sizes listed in
through
are
for copper wiring only. If wire is run in an ambient temperature greater than 30°C, higher temperature wire
and/or larger size wire may be necessary. Wire sizes are based on using the specified breakers.
•
Wire ampacities are chosen from Table 310-16 of the National Electrical Code
®
(NEC
®
). Specification is for
copper wire with a 75º C rating.
•
Material and labor for external wiring requirements are to be provided by designated personnel.
•
If installing a maintenance bypass, a minimum of two separate feeds with upstream feeder breakers, or a
single feed with two upstream feeder breakers, must be provided: one for the UPS or rectifier input
breaker (RIB) (if installed) and one for the maintenance bypass input. DO NOT use a single feed or a single
feeder breaker to supply both the UPS or RIB and the maintenance bypass. If a bypass input breaker (BIB)
is installed in the maintenance bypass and a single-feed UPS is being installed, a single feed to the
maintenance bypass is acceptable for supplying both the UPS and the bypass.
•
The bypass feed into this equipment uses three or four wires. The rectifier feed into this equipment uses
three wires. The phases must be symmetrical about ground (from a Wye source) for proper equipment
operation.
•
The Eaton 9395P 480V unit is designed for operation on a grounded-wye source of supply. There is no
additional connection point for a neutral conductor. The output of this UPS will not directly support phase
to neutral loads.
•
The ISBM and UPM sections are shipped with debris shields covering the ventilation grills on top of the
sections. Do not remove the debris shields until installation is complete. However, remove the shields