INSTALLING OPTIONS AND ACCESSORIES
Eaton Power Xpert 9395P-1200 UPS (1200 kVA, 1200 kW) Installation and Operation Manual
S
P-164000500 Rev 4
www.eaton.com/powerquality
5-11
NOTE
Setup of the Powerware Hot Sync CAN Bridge Card must be performed by an authorized Eaton
Customer Service Engineer. Contact an Eaton service representative to schedule a date.
11.
To check the operation of the RMP II, ensure that the UPS is supplying the load
via inverter or bypass. If the indicators on the RMP II show the appropriate
status, then it is operating correctly.
If the communication link between the UPS and the RMP II is not present, the
RMP II performs a self‐test (all indicators flash and the horn beeps at one‐second
intervals). If the self-test occurs, check all harness connectors and the fuse for
proper seating. If all connections are secure but the RMP II continues to self‐test,
replace the fuse with the spare included in the hardware kit. If a fuse
replacement does not correct the problem, contact an Eaton service
representative for verification that the RMP II is working correctly.
12.
To test the indicator lamps, press and hold the horn silence pushbutton for
three seconds. All lamps should illuminate, and the horn sounds continuously
until you release the pushbutton.
5.4
Installing an Optional Relay Interface Module II
To install RIM II wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See
Chapter 7, “UPS Operating Instructions,” for shutdown instructions.
2.
Perform the procedure listed in paragraph 5.1.
NOTE
If mounting to a hollow wall, secure the enclosure to a wood or metal stud within the wall. Do not
use hollow wall anchors.
3.
Securely mount the RIM II at the desired location. See Figure 5‐13 for mounting
hole locations.
NOTE
When installing signal wiring for CAN card J3 terminals, conduit must be installed between the
device and the UPS cabinet.
4.
Remove the ISBM cabinet top right interface conduit landing plate to drill or
punch conduit holes (see Figure 4‐16).
5.
Reinstall the conduit landing plate.
6.
Install conduit between the UPS and RIM II. See Figure 5‐13 for RIM II knockout
hole location.
7.
Install wiring between the UPS and RIM II. See Figure 5‐2 and Table 5‐1 for the
Powerware Hot Sync CAN Bridge Card terminal location and wiring information,
and Figure 5‐7, Figure 5‐8, and Table 5‐5 for the RIM II terminal location and
wiring information.
NOTE
120 Vac for the RIM II should be supplied from the critical bus by facility planners or the customer.
8.
9.
Close the front door and secure the latch.
Summary of Contents for Power Xpert 9395P-1200
Page 195: ......
Page 196: ... P 1640005004 P 164000500 4 ...