UPS SYSTEM INSTALLATION
Eaton Power Xpert 9395P-1200 UPS (1200 kVA, 1200 kW) Installation and Operation Manual
S
P-164000500 Rev 4
www.eaton.com/powerquality
4-6
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Right Side Shipping
Bracket
Figure 4‐4. Removing the UPM Section Right Side Shipping Bracket
4.3
Mechanically Joining the Sections
NOTE
The following procedure permits the UPS sections to be installed in a location where there is limited
space to slide the sections together from the sides.
NOTE
For the following steps, verify that the forklift or pallet jack is rated to handle the weight of the
section (see Table 3‐1 for cabinet weight).
1.
Using a forklift, move the UPM section to the final installed location.
2.
Remove one top screw and two bottom screws securing the UPM section
wireway panel (see Figure 4‐5). Lift the panel straight up to remove it from the
panel hanger brackets at the top of the cabinet.
3.
Remove the screws securing the top and bottom internal safety shield panels
and remove the panels. Retain the hardware for later use.
4.
Remove the screws securing the corner channel and remove the channel (see
Figure 4‐5). Retain the hardware for later use.