25
9395P 250 kVA / 275 kVA / 300 kVA
User’s and Installation Guide
•
Lift and move the cabinet using only the front or rear forklift slots.
•
Verify that the forklift forks are in a horizontal position before inserting them into the
forklift slots.DO NOT angle fork tips upward.
•
Insert the forks all the way through the base. DO NOT insert forks partially into the base to
move the cabinet.
•
Forks may be partially inserted into the front or rear forklift slots for minor positioning if the
forks are kept in a horizontal position with no upward angling.
•
DO NOT use the forklift slots on the end of the cabinet to move the cabinet.
•
End forklift slots may be used for minor positioning if the forks are kept in a horizontal
position with no upward angling.
•
If these instructions are not followed, damage to the wiring channel and wiring will occur.
NOTE
•
For the following steps, verify that the forklift or pallet jack is rated to handle the weight of
the cabinet (see Table 3-1 for cabinet weight).
• DO NOT reinstall the left side shipping bracket, if installing a Field Installed UPM (FI-UPM).
1.
If not already accomplished, use a forklift or pallet jack to move the cabinet to the installation area,
Or as close as possible, before unloading from the pallet. If possible, move the cabinet using the
pallet.
Insert the forklift or pallet jack forks from the right side of the pallet (facing the cabinet),
between the supports on the bottom of the pallet (see Figure 3
‐
6 binet
center of gravity
measurements). If the cabinet must be moved using the cabinet front or rear fork
lift slots, see the
caution statement at the beginning of this procedure.
2.
Remove the three bolts securing the left side shipping bracket to the cabinet and three bolts
securing the bracket to the pallet (see Figure 4
‐
1). Remove the left side shipping bracket. If
installing the cabinet permanently, retain the shipping bracket and securing hardware for later use.
3.
Remove the three bolts securing the right side shipping bracket to the cabinet and three bolts
securing the bracket to the pallet (see Figure 4
2). Remove the right side shipping bracket. If
installing the cabinet permanently, retain the shipping bracket and securing hardware for later use.
4.
Using a forklift (see the caution statement at the beginning of this procedure), raise the UPS
cabinet section until the cabinet bottom clears the pallet by approximately 3 mm (1/8”).
5.
Pull the pallet from under the UPS cabinet. Discard or recycle the pallet in a responsible
manner.
6.
Using a forklift (see the caution statement at the beginning of this procedure), move the UPS
cabinet to the final installed location.
7.
Carefully lower the UPS cabinet until the cabinet base contacts the floor.
8.
If permanently mounting the system, proceed to Step 9; otherwise, continue to Step 11.
Verify that the fork lift forks are in a horizontal position before inserting them into the fork lift
slots. DO NOT angle fork slots upward.
Summary of Contents for Power Xpert 9395P 250 kVA
Page 1: ...User s and Installation Guide Power Xpert 9395P UPS 250 kVA 275 kVA 300 kVA...
Page 2: ......
Page 3: ...Power Xpert 9395P UPS 250 kVA 275 kVA 300 kVA User s and Installation Guide...
Page 168: ......
Page 169: ......
Page 170: ...614 01919 00...