Eaton
®
Power Xpert
®
9395P-600 (300V-600V) Installation and Operation Manual 164000710—Rev 07
201
1.
Remove one top screw and two bottom screws securing each UPM front panel. Lift each panel straight up
to remove it from the panel hanger bracket at the top of the cabinet.
2.
Remove one top screw and two bottom screws securing the ISBM left front panel. Lift the panel straight
up to remove it from the panel hanger bracket at the top of the cabinet.
3.
If the UPS is a continuous static switch configuration, unfasten the front door latch and swing the door
open (See
4.
Pull the foam filters over the screw heads on the cabinet mounted studs and remove the filters from the
cabinet.
5.
Push the washed or new foam filters over the screw heads on the cabinet mounted studs until seated
against the cabinet.
6.
Reinstall the UPM section front panels removed in Step a and secure with the retained hardware.
7.
Reinstall the ISBM section front panel removed in Step b. and secure with the retained hardware.
8.
If opened, close the front door and secure the latch.
Figure 127. ISBM and UPM Section Air Filter Locations - Continuous Static Switch
ISBM Section
Air Filters
UPM Section
Air Filters
Summary of Contents for Power Xpert 9395P-600/600
Page 8: ......
Page 226: ...16400071007 164000710 07...