Installing Options and Accessories
5-12
Eaton
®
Power Xpert
®
9395P-900 UPS Installation and Operation Manual P-164000501—Rev 09
www.eaton.com/powerquality
11. Contact an Eaton service representative for verification and testing of the RIM II and its connections prior
to making connections with J1 through J4 (see Table 5-6 and Figure 5-9).
You can order interface cables separately for connecting to the 15-Pin D-Sub Connectors.
Figure 5-9. J1, J2, J3, and J4 15-Pin D-Sub Connector
5.5
Installing an Optional Supervisory Contact Module II
To install SCM II wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See Chapter 7, “UPS Operating
Instructions” for shutdown instructions.
2.
Perform the procedure listed in paragraph 5.1.
3.
Securely mount the SCM II at the desired location. See Figure 5-14 for mounting hole locations.
4.
Remove the ISBM cabinet top right interface conduit landing plate to drill or punch conduit holes (see
Figure 4-16).
5.
Reinstall the conduit landing plate.
6.
Install conduit between the UPS and SCM II. See Figure 5-14 for SCM II knockout hole location.
Table 5-6. J1 through J4 Interface Connectors
Status
J1 through J4
Description
UPS AVAILABLE
Pins 1 and 12
Contacts are closed when the UPS is operating in Normal mode or ready to
supply the load.
UPS OFFLINE
Pins 3 and 13
Contacts are open when the UPS is offline. Contacts are closed when the UPS is
operating in Normal mode.
BATTERY WEAK
Pins 5 and 14
Contacts are closed when approximately two minutes of battery time remains
before the critical load is lost.
UTILITY FAILURE
Pins 6 and 15
Contacts are closed when Utility Failure is detected.
15-Pin D
‐
Sub
Connectors
NOTE
If mounting to a hollow wall, secure the enclosure to a wood or metal stud within
the wall. Do not use hollow wall anchors.
NOTE
When installing signal wiring for CAN card J3 terminals, conduit must be installed
between the device and the UPS cabinet.
Summary of Contents for Power Xpert 9395P-900 Series
Page 2: ......
Page 8: ...This page intentionally left blank...
Page 33: ...Section I Installation...
Page 34: ......
Page 139: ...Section II Operation...
Page 140: ......
Page 231: ......
Page 232: ...P 164000501 6 P 164000501 9...