FIELD INSTALLED UPM INSTALLATION PLAN AND UNPACKING
Power Xpert
9395P Field Installed UPM Mechanical Installation Manual
S
P-164000503 Rev 1
3-7
NOTE
For the following step, verify that the forklift or pallet jack is rated to handle the weight of the
cabinet (see Table 3‐1 on page 3-2 for cabinet weight).
2.
Use a forklift or pallet jack to move the packaged cabinet to the installation site,
or as close as possible, before unpacking. If possible, move the cabinet using the
pallet. Insert the forklift or pallet jack forks from the right side of the pallet (facing
the cabinet), between the supports on the bottom of the pallet (see Figure 3‐6
for the FI-UPM cabinet center of gravity measurements).
C
A
U
T
I
O
N
Do not tilt the FI-UPM cabinet more than 10° from vertical or the cabinet may tip over.
A
T
T
E
N
T
I
O
N
!
Ne pas incliner les armoires FI-UPM à plus de 10 degrés de la verticale puisqu’elles pourraient se renverser.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft)
on each side for removing the cabinet from the pallet.
NOTE
The FI-UPM cabinet is shipped with a debris shield covering the ventilation grill on top of the unit.
Do not remove the debris shield until installation is complete.
4.
Remove the protective covering from the cabinet.
5.
Remove the packing material, and discard or recycle in a responsible manner.
6.
Inspect the contents for any evidence of physical damage, and compare each
item with the Bill of Lading. If damage has occurred or shortages are evident,
contact an Eaton service representative immediately to determine the extent of
the damage and its impact on further installation.
NOTE
While waiting for installation, protect the unpacked cabinet from moisture, dust, and other harmful
contaminants. Failure to store and protect the FI-UPM properly may void your warranty.