INSTALLATION
Eaton 9140 UPS (7.5–10 kVA) User's Guide
S
164201622 Rev 3
www.eaton.com/powerquality
57
17.
If an emergency power-off (disconnect) switch is required by local
codes, see “REPO and ROO Installation” on page 58 to install the
REPO switch before powering on the UPS.
If you are not required to install a REPO switch, you can install an
optional remote on/off (ROO) switch (see page 58).
18.
Switch the main utility breaker on.
19.
Switch all circuit breakers to the ON (
|
) position.
The
indicator flashes, indicating the UPS is in Standby mode
with the equipment offline. The fans run and the LCD illuminates
and displays the UPS startup screens.
20.
To change the factory-set defaults, see “User Settings” on
page 64.
21.
Turn the UPS on by selecting MENU from the system status
screen, then select CONTROL, OUTPUT CONTROL, UPS TO
ONLINE, and OK to confirm.
The
indicator illuminates solid. The UPS is now in Normal mode
and supplying power to your equipment.
If the alarm beeps or a UPS alarm indicator stays on, see
“Troubleshooting” on page 95.
22.
If you installed an optional REPO or ROO, test the REPO or ROO
function:
Activate the external REPO or ROO switch. Verify the status
change on the UPS display.
Deactivate the external REPO or ROO switch and restart the UPS.
23.
If optional EBMs are installed, continue to “Configuring the UPS for
EBMs” on page 72.
NOTE
The batteries charge to 80% capacity in less than 5 hours. However, it is
recommended that the batteries charge for 48 hours after installation or long-term storage.