INSTALLATION
Eaton
®
9140 (9910-E82/E83) UPS Installation Guide for IBM
®
Applications
S
164201715 Rev 2
www.eaton.com/ibm
6
EBM Setup
The E82/E83 EBM comes with all hardware required for installation in a
standard EIA or JIS seismic rack-mount configuration with square or
round mounting holes. The rail assemblies adjust to mount in 48-cm
(19-inch) panel racks from 61 to 84 cm (24 to 33 inches) deep [72 to
81 cm (28.5 to 32 inches) deep if installing the optional seismic
mounting brackets].
Checking the EBM Accessory Kit
If you purchased an optional EBM, verify that the following items are
included with the EBM (PN 44V3921):
NOTE
If the EBM is factory-installed in an IBM rack, these items are pre-assembled.
S
Mounting brackets and fasteners (if not already installed):
-
(2) front mounting brackets
-
(2) rear mounting brackets
-
(12) M4 flat-head screws, plus (2) extra
S
Rails and fasteners:
-
(2) sliding rail assemblies (left and right)
-
(4) adapter plates (for 7.1 mm round hole)
-
(4) adapter plates (for 9.5 mm square hole)
-
(16) M5 machine screws, plus (2) extra
-
(2) M6 machine screws, plus (2) extra
-
(2) M6 clip nuts for racks with round holes, plus (2) extra
-
(2) M6 cage nuts for racks with square holes, plus (2) extra
-
(8) M4 machine screws with (8) M4 locknuts, plus (2) extra of each
S
Optional seismic mounting brackets and fasteners:
-
(2) EBM seismic mounting brackets
-
(4) wing bolts, plus (1) extra
-
(4) M6 machine screws
S
EBM user's guide (located in the carton labeled 9910-6646 Acc Kit,
PN 44V3922)
NOTE
Discard the EBM user's guide if you are installing the EBM with a new UPS at the
same time. Use the UPS user's guide instead to install both the UPS and the EBM.