INSTALLATION
EATON
Powerware
®
BladeUPS
®
(12 kVA) User's Guide
S
164201649 Rev 3
www.powerware.com
70
16.
To change any other factory-set defaults, see “Operation” on
page 71.
NOTE
It is recommended to set the Date and Time and the Start Screen.
NOTE
Verify that the Parallel Operation Settings are set appropriately for your system. For
example, if you know the load will exceed the redundancy level of the system, set the Parallel
Operation Mode to “Capacity Mode” to prevent unnecessary alarms.
NOTE
For a parallel-ready system (a single UPS installed to be part of a future parallel
system), set the Parallel Operation Settings / Parallel Operation Mode to “Capacity Mode” to
prevent unnecessary alarms.
17.
If you installed an optional REPO, test the REPO function:
Activate the external REPO switch. Verify the status change on the
UPS display.
Deactivate the external REPO switch and restart the UPS.
NOTE
The batteries charge to 80% capacity in less than 5 hours. However, it is
recommended that the batteries charge for 48 hours after installation or long-term storage.
18.
See “Updating the UPS Firmware” on page 112.
NOTE
When adding a new UPS to a parallel system or updating one UPS's firmware, verify
that all UPSs in the parallel system are updated to the same firmware version.