FIELD INSTALLED UPM INSTALLATION
EATON
9395 Field Installed UPM Mechanical Installation Manual
S
164201717 Rev 3
www.eaton.com/powerquality
4−6
Installation Checklist
-
All packing materials and restraints have been removed from the cabinet.
-
UPS cabinet wire entry plate and knockout have been removed from the cabinet.
-
The FI−UPM cabinet is placed in its installed location.
-
A cabinet grounding/mounting kit is installed between the FI−UPM and UPS cabinets.
-
All cables are properly routed from the FI−UPM to the UPS.
-
Air conditioning equipment is installed and operating correctly.
-
The area around the installed UPS system is clean and dust-free. (It is recommended that the UPS be installed on a
level floor suitable for computer or electronic equipment.)
-
Adequate workspace exists around the FI−UPM and UPS cabinets.
-
Adequate lighting is provided around all UPS equipment.
-
A 120 Vac or 230 Vac service outlet (depending on local mains voltage) is located within 7.5 meters (25 feet) of the
UPS equipment.
-
The debris shield covering the FI−UPM cabinet ventilation grill is removed.
-
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.