INSTALLATION
EATON
BladeUPS
®
(12 kVA) User's Guide
S
164201649 Rev 4
www.eaton.com/powerquality
20
6.
Verify that the leveling feet are long enough to lower to the floor. Leveling feet
that function solely as pallet bolt supports may need to be replaced with longer
versions. For safety, have one person tilt the cabinet while a second person
switches the feet.
7.
Optional.
For ease of installation, remove the rack side panels, especially the
panel on the side nearest the BladeUPS Bar.
8.
Plan where each cabinet will be located in the rack and determine the “U” marks
to use for mounting the rails. For example, for a rack containing six UPSs and a
bottom wireway, plan to mount the bottom of the rails at the following marks
(see Figure 3):
7
13
19
25
31
37
7
Figure 3. Recommended Rail Locations (Example Configuration)
NOTE
Recommended rail locations are for example only. Adjust the locations as needed for your system's
configuration. Allow for hole spacing and numbering (see Figure 3). For guidelines for configuring a parallel
system with EBMs, see page 3.
9.
Continue to the following section, “Installing the Input and Output Wiring.”
Summary of Contents for Powerware Series
Page 1: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 2: ......
Page 3: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 84: ...OPERATION EATON BladeUPS 12 kVA User s Guide S 164201649 Rev 4www eaton com powerquality 76 ...
Page 119: ......
Page 120: ... 1642016494 164201649 4 ...