INSTALLATION
EATON
BladeUPS
®
(12 kVA) User's Guide
S
164201649 Rev 4
www.eaton.com/powerquality
42
Standalone UPS Installation
NOTE
Do not make unauthorized changes to the UPS; otherwise, damage may occur to your equipment and
void your warranty.
The BladeUPS modules require a dedicated branch circuit that meets the following
requirements:
S
50A (BladeUPS 12 module) or 30A (BladeUPS 12i module) circuit with overcurrent
protection
S
Three-phase, 4-wire plus ground, 208Y/120V nominal (BladeUPS 12 module) or
400Y/230V nominal, 380–415 Vac acceptable (BladeUPS 12i module)
S
50/60 Hz
S
Wall-mounted breaker that is readily accessible to the operator
To install the UPS:
1.
Switch off utility power to the distribution point where the UPS will be
connected. Be absolutely sure there is no power.
2.
Verify that all circuit breakers are in the OFF (O) position.
NOTE
The load connector breaker controls the load connector only, not the output power cord.
3.
If you are installing power management software, connect your computer to the
UPS communication port or optional X-Slot card (see page 77). For the
communication port, use the supplied serial cable.
4.
If your rack has conductors for grounding or bonding of ungrounded metal parts,
connect the ground cable (not included) to the ground bonding screw.
See Figure 32 for the location of the ground bonding screw.
5.
If an emergency power-off (disconnect) switch is required by local codes, see
“Remote Emergency Power-off” on page 83 to install the REPO switch before
powering on the UPS.
6.
Continue to “Standalone UPS Initial Startup” on page 59.
Summary of Contents for Powerware Series
Page 1: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 2: ......
Page 3: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 84: ...OPERATION EATON BladeUPS 12 kVA User s Guide S 164201649 Rev 4www eaton com powerquality 76 ...
Page 119: ......
Page 120: ... 1642016494 164201649 4 ...