INSTALLATION
EATON
BladeUPS
®
(12 kVA) User's Guide
S
164201649 Rev 4
www.eaton.com/powerquality
52
11.
If your rack has conductors for grounding or bonding of ungrounded metal parts,
connect the ground cable (not included) to the ground bonding screw. See
Figure 32 on page 43 for the location of the ground bonding screw.
12.
You can install an optional REPO circuit that will shut down the entire
parallel-ready system using a single switch. See “Remote Emergency Power-off”
on page 83 to install the REPO switch before powering on the parallel-ready
system.
13.
Connect the parallel input cord from the UPS to the BladeUPS Bar in the rack as
shown in Figure 37 on page 49.
Gently loop and twist the parallel input cord as shown to minimize stress on the
cord. The loop and twist for the cord may vary depending on configuration and
strain relief.
14.
Continue to “Parallel System Initial Startup” on page 60.
Summary of Contents for Powerware Series
Page 1: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 2: ......
Page 3: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 84: ...OPERATION EATON BladeUPS 12 kVA User s Guide S 164201649 Rev 4www eaton com powerquality 76 ...
Page 119: ......
Page 120: ... 1642016494 164201649 4 ...