22
External Battery Cabinets
4 .6
Initial Startup
4 .7
Completing the Installation Checklist
The Installation Checklist MUST be completed prior to starting the UPS system for
the first time.
NOTE
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms specified become void. This service is offered as part of the sales contract for the EBC. Contact
an Eaton service representative in advance (usually a two-week notice is required) to reserve a preferred
startup date.
The final step in installing the EBC is completing the following Installation Checklist. This checklist ensures that
you have completely installed all hardware, cables, and other equipment. Complete all items listed on the
checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain
the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
Installation Checklist:
•
All packing materials and restraints have been removed from each cabinet.
•
The EBC is installed on a level floor suitable for computer or electronic equipment.
•
The EBC is placed in its installed location
•
All conduits and cables are properly routed between the EBC and the UPS.
•
All power cables are properly sized and terminated.
•
A ground conductor is properly installed.
•
All terminal cover plates (if have) are installed.
•
Air conditioning equipment is installed and operating correctly.
•
The area around the UPS system is clean and dust-free.
•
Adequate workspace exists around the EBC and other cabinets.
•
Adequate lighting is provided around all EBC and UPS equipment.
•
A 230 Vac service outlet is located within 7.5 metres (25 feet) of the EBC and UPS equipment
•
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
Summary of Contents for Single EBC
Page 1: ...External Battery Cabinets Installation and Operation Manual Eaton UPS Accessories...
Page 2: ......
Page 29: ...23 External Battery Cabinets Notes...
Page 34: ......
Page 35: ......
Page 36: ...614 01726 01...