21
5. Installation
7. Place the cabinet on a level surface as close as
possible to its final position.
8. Move the cabinet into its final operating position.
Adjust one front foot to level and immobilize the
unit, then adjust the other support foot accordingly
to ensure the unit is level.
5.2 Selecting Installation Position
Select a proper environment to install the unit, in order to minimize the possibility of damage to the battery system and
maximize the life of the batteries.
1. Do not block air flow to the ventilation openings of the unit.
2. Ensure environmental conditions of the installation site are in accordance with the unit specifications to avoid
overheat and excessive moisture. Refer to section
4.2 Physical Requirements.
3. Do not place the unit in a dusty or corrosive environment or near any flammable objects.
4. The unit is not designed for outdoor use.
Notes:
• Place the battery cabinet in a clean, stable environment. Avoid vibration, dust, humidity, flammable gases, liquids and corrosives.
• To help prevent high temperatures in the room where the UPS is installed, extractor fans and/or cooling systems are
recommended.
• Batteries should be mounted in an environment where the temperature is within the required specifications. Temperature is a key
factor in determining battery life and capacity. Battery temperature should be maintained between 59°F to 77°F (20°C to 25°C).
Keep batteries away from heat sources, main air ventilation areas, etc.
WARNING!
Typical battery performance data reflects an operating temperature between 59°F to 77°F (20°C
to 25°C). Operating the UPS above this range will reduce the battery life, while operating the UPS
below this range will reduce battery capacity.
• If the UPS will not be installed immediately, it must be stored in a room without excessive heat or humidity.
Summary of Contents for Smart Online S3M BP240V09
Page 38: ...38 5 Installation Figure 5 32 Wiring Diagram for Installation of 80 Batteries ...
Page 46: ...46 5 Installation Figure 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Page 49: ...49 5 Installation Figure 5 44A 2 Remove top right side and left side plates Figure 5 44 ...
Page 54: ...54 5 Installation 14 Reinstall the covers and the screws Figure 5 53 Figure 5 53 ...
Page 113: ...113 5 Instalación Figura 5 32 Diagrama de Cableado para la Instalación de 80 Baterías ...
Page 121: ...121 5 Instalación Figura 5 41C Frente Capa 3 Capa 2 Capa 1 Atrás ...
Page 129: ...129 5 Instalación 14 Reinstale las cubiertas y los tornillos Figura 5 53 Figura 5 53 ...
Page 196: ...196 5 Installation Figure 5 41C Avant Couche 3 Couche 2 Couche 1 Arrière ...
Page 204: ...204 5 Installation 14 Réinstaller les couvercles et les vis Figure 5 53 Figure 5 53 ...