Step 4: Setting Chg. cur. limiting coef (C)
The charging current limit is a multiple of the battery capacity. It is used to set the battery boost charging time limit. The
value can be 0.05~0.25, and is 0.25 by default. Obtain the
Charging (Chg) current (cur) limiting coefficient (C)
based
on the specific S3M UPS and battery cabinet model combination from the chart in
Section 6.4
.
Float and Boost Voltage:
The UPS is factory-set for proper float (2.27V/cell, 13.62V/battery) and boost (2.35V/cell,
14.1V/battery) voltages.
Cell float voltage:
The float voltage value can be 2.23~2.30 V/cell. The default value is 2.27 V/cell.
Cell boost voltage:
The battery equalized voltage value can be 2.30~2.40 V/cell. The default value is 2.35 V/cell.
Step 5: Setting Aver Changing Duration (min)
Setting the Average Charging Duration in minutes is an estimation of the boost charger time duration to charge new
batteries to 90% capacity at 25°C. Obtain the recommended Average (Aver) Charging Duration (min) number based on
the specific S3M UPS and battery cabinet model combination from the chart in
Section 6.4
. Note the recommended
battery boost charge durations are estimates only based on new batteries. These numbers may change with the age
of the batteries and the battery ambient temperature. To change the
Aver Charging Duration
, press directly on the
defaulted 240 value in the display.
The Average (Aver) charging duration is the battery boost charge time limit. The value can be 1~999 min. The default is
value 240 (4 hours).
Summary of Contents for Smart Online S3M BP240V09
Page 38: ...38 5 Installation Figure 5 32 Wiring Diagram for Installation of 80 Batteries ...
Page 46: ...46 5 Installation Figure 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Page 49: ...49 5 Installation Figure 5 44A 2 Remove top right side and left side plates Figure 5 44 ...
Page 54: ...54 5 Installation 14 Reinstall the covers and the screws Figure 5 53 Figure 5 53 ...
Page 113: ...113 5 Instalación Figura 5 32 Diagrama de Cableado para la Instalación de 80 Baterías ...
Page 121: ...121 5 Instalación Figura 5 41C Frente Capa 3 Capa 2 Capa 1 Atrás ...
Page 129: ...129 5 Instalación 14 Reinstale las cubiertas y los tornillos Figura 5 53 Figura 5 53 ...
Page 196: ...196 5 Installation Figure 5 41C Avant Couche 3 Couche 2 Couche 1 Arrière ...
Page 204: ...204 5 Installation 14 Réinstaller les couvercles et les vis Figure 5 53 Figure 5 53 ...