background image

15

Instruction Booklet 

IB02201004E

Effective October 2017 

Revision #4

Instructions for installation, operation, and 

maintenance of 38 kV type VacClad-W, 

150 BIL switchgear indoor housings 

EATON

 www.eaton.com

Section 6: Inspection and maintenance

6.1 Safety precautions

Refer to the Safety precautions section of this manual .

 WARNING

WHEN INSPECTING, REPAIRING, AND PERFORMING MAINTENANCE ON 

SWITCHGEAR, THE FACT THAT DANGEROUS VOLTAGES MAY EXIST MUST 

BE KEPT IN MIND.  PRECAUTIONS MUST BE TAKEN TO ENSURE THAT 

PERSONNEL DO NOT COME IN CONTACT WITH ENERGIZED HIGH VOLTAGE 

PARTS.  FAILURE TO DO SO COULD RESULT IN DEATH, PERSONAL INJURY, 

OR PROPERTY DAMAGE.

Some common general precautions for high voltage work are:

Connections

All connections should be considered energized until the crew 

expecting to work on them is ensured that the circuits are de-

energized, and until every possible precaution has been taken to see 

that there is no chance of a circuit being energized while the crew is 

working .

Switches

Switches, which have been opened to de-energize a circuit to permit 

work on equipment, should be locked or blocked open, and a suit-

able visible warning device placed on them .

Grounding

Do not work on parts normally carrying current at high voltage until 

these parts have been disconnected and grounded to the ground 

bus .  The purchaser should make provision for connecting adequate 

flexible ground leads to every part of the switching equipment .

6.2 Access to switchgear parts
6.2.1 High voltage parts

VacClad-W switchgear is a metal-clad design .  All major parts of the 

primary circuit are isolated by grounded metal barriers and enclosed 

within separate compartments .  For example, the circuit breaker, 

main bus, and primary line and load terminations are isolated from 

each other and enclosed in separate compartments, which are made 

from grounded metal barriers and covers .  Access to high voltage 

parts can be gained by removing the covers and barriers .  The covers 

and barriers should not be removed unless the parts to be exposed 

are de-energized .

6.2.2 Main contacts

Stationary primary disconnecting contacts (spouts) are located 

behind the automatic safety shutters in the breaker compartment .  

Upper and/or lower spouts can be exposed by manually opening the 

shutters (see Figures 10 and 11) .  Do not expose any contacts unless 

all upper and lower high voltage parts are de-energized .

 WARNING

FAILURE TO DO SO COULD RESULT IN DEATH, PERSONAL INJURY, OR 

PROPERTY DAMAGE.

6.2.3 Current transformers

Window type current transformers are installed over the stationary 

primary disconnecting contacts (spouts) in the front of the unit (see 

Figure 11) .  All primary circuits must be de-energized prior to gaining 

access to any current transformers .

 WARNING

FAILURE TO DO SO COULD RESULT IN DEATH, PERSONAL INJURY, OR 

PROPERTY DAMAGE.

6.2.4  Tranformers and primary fuses

A .  Removing transformers from the auxiliary compartment and 

replacing fuses:
1 .  Follow the instructions in the Installation procedure section 

of this manual, to remove the transformer drawer from the 

auxiliary compartment .  With the transformer(s) removed 

from the unit, unscrew the contact spring retaining screws 

(2) located at the end of the fuse tube .  Remove the fuse 

from the tube and replace with a new fuse .  Reinstall the 

contact spring on the new fuse and install the contact retain-

ing screws (see Figure 8) .

6.2.5 Control equipment

With the exception of apparatus such as current transformers and 

rear-mounted heaters, control equipment and wiring is generally 

accessible without exposing high voltage parts .

6.3 Inspection and maintenance schedule

To ensure high-quality service, a definite maintenance schedule, 

systematically followed, is essential .  Plant, operating, and local con-

ditions vary to such an extent that the schedule must be prepared 

to suit the conditions .  However, the following general requirements 

should be helpful in setting up the program .

 WARNING

BEFORE ATTEMPTING ANY INSPECTION OR MAINTENANCE, BE SURE 

THAT ALL PRIMARY AND CONTROL CIRCUITS HAVE BEEN DE-ENERGIZED 

AND GROUNDED AS REQUIRED, AND THAT PROPER STEPS HAVE BEEN 

TAKEN TO BE SURE THAT THEY WILL REMAIN DE-ENERGIZED UNTIL ALL 

WORK IS COMPLETED.  FAILURE TO DO SO COULD RESULT IN BODILY 

INJURY OR ELECTROCUTION.  WHEN ENERGIZED, CIRCUIT CARRIES 

LETHAL HIGH VOLTAGE.

6.3.1 Individual devices

The maintenance schedule for individual devices such as circuit 

breakers, relays, and so on, should be based upon recommendations 

contained in the individual instruction book for the device .  These 

operations should be coordinated with the overall program to result 

in the least operating inconvenience and circuit shutdown .

6.3.2 Overall maintenance

The switchgear installation should be given a thorough overall 

maintenance check at the end of the first year in service because 

it provides an opportunity to evaluate conditions at an early point in 

the life of the equipment .  Where conditions are abnormal, more fre-

quent inspection and maintenance is necessary .  Where conditions 

warrant, a longer period of time between maintenance periods may 

be used .  The following require attention .

1 . 

Buses and connections

De-energize the primary circuits and remove the cover plates 

from the primary compartments .  Before cleaning, take  

megohmmeter (megger) readings between phases and each 

phase to ground .  Inspect for signs of overheating or weakened 

insulation .  Remove dust from buses, connections, supports, and 

enclosure surfaces .  A vacuum cleaner with a long nozzle will be 

of assistance .  Wipe clean with distilled water and wipe dry .
After buses have been dusted and wiped clean, take megger 

readings again between phases and each phase to ground .  Keep 

a record of these readings for future reference in determining 

when trends occur that would indicate a lowering of the insula-

tion resistance .
Periodic high-potential tests are not required after initial start-up 

and are recommended only after repair of high voltage buses or 

installation, or when the trend of megger readings indicates it to 

be advisable .  Refer to Table 1 .

Summary of Contents for VacClad-W

Page 1: ...Operation of the system 14 Inspection and maintenance 15 Lubrication 17 Renewal parts 17 Accessories 18 Metal clad switchgear field taping procedure 38 kV 23 Instructions for installation operation and maintenance of 38 kV type VacClad W 150 BIL switchgear indoor housings Instruction Booklet IB02201004E Effective October 2017 Revision 4 ...

Page 2: ...2 Instruction Booklet IB02201004E Effective October 2017 Revision 4 Instructions for installation operation and maintenance of 38 kV type VacClad W 150 BIL switchgear indoor housings EATON www eaton com ...

Page 3: ...t The sole source governing the rights and remedies of any purchaser of this equipment is the contract between the purchaser and Eaton NO WARRANTIES EXPRESSED OR IMPLIED INCLUDING WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR MERCHANTABILITY OR WARRANTIES ARISING FROM THE COURSE OF DEALING OR USAGE OF TRADE ARE MADE REGARDING THE INFORMATION RECOMMENDATIONS AND DESCRIPTIONS CONTAINED HEREIN In...

Page 4: ...tion Eaton s VacClad W 38 kV 150 BIL switchgear indoor housing assem bly provides centralized control and protection of medium voltage power equipment and circuits in industrial commercial and util ity installations involving generators motors and feeder circuits Several built in interlocks and safety features are provided The construction of the VacClad W 38 kV 150 BIL switchgear pro vides the en...

Page 5: ...hardware is in place and torqued per Section 2 3 Table 3 8 Confirm that no tools or objects are left inside the enclosure 9 Confirm that all devices covers doors panels and so on are in place 10 Before start up perform a field power frequency withstand Hi Pot test using test voltages given in Table 1 Table 1 Power Frequency Withstand Test Voltages Rated Maximum Voltage kV Power Frequency Withstand...

Page 6: ...on Bronze 5 6 78 10 13 56 15 20 34 40 54 24 55 74 58 Figure 1 Tie bolt Locations 31 33 1 2 3 4 5 6 7 8 9 12 13 10 17 16 32 33 15 14 31 24 25 22 23 20 21 19 18 26 27 28 29 30 B Remove the rear covers or open the rear doors if applicable of the cells on the sides of all the shipping split Remove from these sections the angled metal barrier and vertical main bus barrier from the cable compartment in ...

Page 7: ...tations and larger substations the ground resistance should be 1 ohm or less For industrial plants and small substations the ground should be less than 5 ohms the NEC states that the ground resistance should never exceed 25 ohms Ground Link Step 5 Connect the high voltage bus between the shipping sections A Remove the rear covers or open the rear doors if applicable of any remaining cells that wer...

Page 8: ...necting the cables to them Use the flexible connectors to connect the arial lugs to the conductors This will keep strain off the insulators of the pothead or the terminator Tape or otherwise insulate the entire joint including the flexible connectors see the Metal clad switchgear field taping procedure 38 kV section in this manual G If zero sequence transformers are used pass the power cables thro...

Page 9: ... removal of the drawers from the units prior to performing the following actions After removing the drawers check for any damage to the transformers transformer fuses and fuse tubes drawers and cell parts Figure 6 Auxiliary Compartment with Front Cover Installed Cover Interlock Bracket Cover Guide Racking Cover Plate Viewing Window Cover Guide Perimeter Bolting Cover Guide Figure 7 Auxiliary Compa...

Page 10: ...onnect position Use the lighting out or ringing methods to verify 3 Verify that the primary shutters are open and have operated properly The shutters can be viewed from within the closed compartment through the viewing window on the front cover 4 The front cover can not be removed when a transformer drawer is in the Connect position The transformer drawer must be in the Disconnect position to remo...

Page 11: ...BODILY INJURY AND PROPERTY DAMAGE Figure 10 Breaker Compartment with Shutters Closed Safety Shutters Lock Closed Bracket Figure 11 Breaker Compartment with Shutters Latched Open 3 Ring type current transformers The ring type current transformers are mounted so they slip over the primary disconnecting contact insulating high voltage termi nals at the rear wall of the breaker compartment There is sp...

Page 12: ...ly withdrawn position 2 Move the LOTO slider to the left in order for the LOTO slider to engage the slider used for racking Refer to 6 in Figure 15 3 Insert a LOTO option see Figure 14 into the circuit breaker pan LOTO provisions see Figure 13 4 When it is safe to do so remove the lock to allow the LOTO slider to move to the right when racking the break er is required Figure 13 Lockout Tagout Prov...

Page 13: ...es when the breaker is in the fully connected position Represents positive indication of the breaker in the Connect posi tion by use of a red flag that rotates into viewing position when the breaker is fully connected 8 Slider interlocks prevent removing a closed breaker 9 The mechanism operated cell MOC switch is an assembly of switches that is operated by a lever on the breaker mechanism Refer t...

Page 14: ...stallation or test handle them carefully Replace the covers as soon as possible to keep dust and dirt out of the components Step 6 Perform a loading check of the control circuits Before energizing the control circuits check the control bus with an ohmmeter to make sure there are no short circuits in the control wiring If an ohmmeter is not available connect a small fuse in series with the source o...

Page 15: ...eplacing fuses 1 Follow the instructions in the Installation procedure section of this manual to remove the transformer drawer from the auxiliary compartment With the transformer s removed from the unit unscrew the contact spring retaining screws 2 located at the end of the fuse tube Remove the fuse from the tube and replace with a new fuse Reinstall the contact spring on the new fuse and install ...

Page 16: ...ections and test are recommended in the battery supplier s instructions At the same time the battery is checked inspect the battery charger and remove accumulations of dust and dirt On all chargers having a manual transfer switch for setting the charging rate check carefully to be sure that the selector switch is returned to the value appropriate for a floating charge at the end of the periodic in...

Page 17: ...o 53701QB The appli cation of the lubricants should be held to a minimum to reduce the accumulation of dust and dirt 7 1 Where to lubricate 1 MOC switch refer to 9 in Figure 15 Grease Eaton Electrical Material No 53701QB should be applied to the three locations where the rotary switch assemblies link to the Push Bar assem bly see Figure 16 This should be done at least every three years Figure 16 L...

Page 18: ...t jumper is used for electrically operating the circuit breaker outside its compartment 9 2 Optional accessories 9 2 1Test cabinet A test cabinet is used for electrically opening and closing of the breaker when it is outside its housing The cabinet includes termi nals for control power connections a set of pull out fuse blocks for control power disconnect necessary control equipment and a cable ha...

Page 19: ...y to oper ate the lifter and transformer pan with a transformer drawer A Securing the lifter pan to the lifter 1 Expand the lifter base legs so they span the lifter pan To do this unscrew and remove the adjustment bolts and pull each leg outward until the third hole in each leg is in line with each mating through hole This exposes two of the three leg holes as shown in Figure 22 Screw the bolts ba...

Page 20: ... tion of the drawer is butted up against the lower section of the drawer see Figure 9 3 Roll the drawer onto the lifter pan and up against the rubber stops Use the pan rails as a guide see Figure 27 NOTICE DO NOT HANDLE THE FUSE TUBES AND MATING PARTS WHILE MOVING THE TRANSFORMER DRAWER THIS MAY CAUSE DAMAGE TO THESE PARTS Figure 25 Break Pedal for Locking the Lifter 4 Make sure the drawer safety ...

Page 21: ... The guide stops butt up against the switchgear side sheets and prevent the lifter from moving too far into the compart ment As the pan is moved into place pan safety latches bias off the switchgear side sheets and latch to the side sheet flanges when the pan is fully in place These safety latches along with the lifter brake prevent the lifter and pan from backing out of the compartment when the d...

Page 22: ...awer from the cell 7 Pull the drawer using the red release lever onto the lifter pan making sure that the wheels on the drawer roll on the pan between the pan rails Pull the drawer all the way back on the pan and up against the rubber stops NOTICE DO NOT HANDLE THE FUSE TUBES AND MATING PARTS WHILE MOVING THE TRANSFORMER DRAWER THIS MAY CAUSE DAMAGE TO THESE PARTS 8 Make sure the drawer safety lat...

Page 23: ...igh voltage EPR insulating tape Trade name Scotch 130C 10 2 Using an insulating boot Step 1 Clean the area of dirt and foreign matter Use a clean dry cloth or if necessary dampen slightly with distilled water Do not use any abrasives or solvents Step 2 Place the boot over the joint so it fits in place Fasten together with plastic wire ties Cut off excess ends of plas tic wire ties 10 3 Cable termi...

Page 24: ...LUDES A BAND OF TAPE CONSISTING OF ONE OR MORE TURNS WRAPPED DIRECTLY ON TOP OF EACH OTHER LAYER INSULATING TAPE 1 INCH WIDE WRAPPED FROM ONE END OF THE JOINT TO THE OTHER OR TO A PAD SO EACH SUCCEEDING TURN LAPS THE PREVIOUS TURN BY THE AMOUNT SPECIFIED IN THE CHART OVERLAP A SPECIFIED DISTANCE MEASURED ALONG THE PRE INSULATION STARTING FROM THE POINT WHERE THE PRE INSULATION ENDS AND THE EXPOSED...

Page 25: ...ections must be made DWG NO MODEL REV SHEET OF TITLE ALL REV NOTES LISTED ON SHT 1 REV MODEL FILENAME T BLK REV 4 C 7819C90 2 2 4 JOINT TAPING THRU JOINTS WITH HARDWARE 1 CLEAN AREA OF DIRT AND FOREIGN MATTER 2 WIPE PREINSULATION WITH ISOPROPYL ALCOHOL 3 APPLY FILLER OVER BARE CONDUCTOR AND HARDWARE TO COVER AND SMOOTH OUT THE SURFACE BLEND CONTOUR INTO PRE INSULATION SURFACES TRY TO PREVENT AIR P...

Page 26: ...ransformers Insulated pothead bushing Pothead ground lead must be carried through the Zero Sequence current transformer and solidly grounded on the load side of the ct as shown Use 6 wire with 600V insulation Power Cables Conduit when used Cable connections to switchgear terminals when used with Insulated Pothead Conduit must be terminated and solidly grounded on the load side of the current trans...

Page 27: ...struction Booklet IB02201004E Effective October 2017 Revision 4 Instructions for installation operation and maintenance of 38 kV type VacClad W 150 BIL switchgear indoor housings EATON www eaton com Notes N ...

Page 28: ...ved Printed in USA Publication No IB02201004E TBG001315 October 2017 Eaton is a registered trademark All other trademarks are property of their respective owners Instructions for installation operation and maintenance of 38 kV type VacClad W 150 BIL switchgear indoor housings Instruction Booklet IB02201004E Effective October 2017 Revision 4 ...

Reviews: