xChargeIn
Calibrate the device
Manual for MID variants V1.01
20
© EATON
6.2
Activate/deactivate MID test mode
MID test mode is activated and deactivated in the charging station connec-
tion panel. To access the connection panel, the housing cover and the con-
nection panel cover must be removed. For a description of how to remove
the covers, see "Operating Instructions".
Fig. 6-6: Connection panel: Elements for activating/deactivating the test mode
DSW
... DIP switch
X6
... Pin strip for jumpers
Activate MID test mode
Necessary aids: Jumper
To activate the MID test mode, proceed as follows:
1) Switch off the supply voltage of the charging station.
2) Set the jumper on the pin strip for the jumper
X6
.
3) Set the DIP switches for the charging current to 32 A:
DSW1.6
to
ON
DSW1.7
to
OFF
DSW1.8
to
ON
4) Set the DIP switch for commissioning mode
DSW2.8
to
ON
.
5) Switch on the supply voltage of the charging station.
MID test mode is activated.
Deactivate MID test mode
To deactivate the MID test mode, proceed as follows:
1) Switch off the supply voltage of the charging station.
2) Remove the jumper from the pin strip
X6
.
3) Set the DIP switch for commissioning mode
DSW2.8
to
OFF
.
4) Set the DIP switches for the charging current back to the original value.