background image

Operating instructions

R3G250-AY11-C1

Translation of the original operating instructions

4.3.2 Connecting wires to terminals

WARNING
Live terminals and connections even with device
switched off

Electric shock
→ Wait five minutes after disconnecting the voltage at all poles

before opening the device.

;

Remove the cap from the cable gland.

Only remove caps where cables are fed in.

;

Route the wire(s) (not included in scope of delivery) into the terminal
box.

;

First connect the "PE" (protective earth).

;

Connect the wires to the corresponding terminals.

Use a screwdriver to do so.
When connecting, ensure that no wire ends fan out.

Fig. 2: Connecting wires to terminals

;

Seal the terminal box.

4.3.3 Cable routing

Water must be prevented from reaching the cable gland along the cable.

NOTE
Damage caused by moisture penetration.

Moisture can penetrate into the terminal box if water is
constantly present at the cable glands.
→ To prevent the constant accumulation of water at the cable

glands, the cable should be routed in a U-shaped loop
wherever possible.

→ If this is not possible, a drip edge can be produced by

fitting a cable tie directly in front of the cable gland for example.

When routing the cable, make sure that the cable glands are located at
the bottom. The cables must always be routed downward.

Fig. 3: Cable routing for fans installed upright.

4.4 Factory settings

Factory settings made for the device by ebm-papst.

Mode parameter set 1

PWM control

Mode parameter set 2

PWM control

Fan/device address

1

Max. PWM / %

100

Min. PWM / %

5,1

Save set value to
EEPROM

Yes

Set value requirement

Analog (linear)

Direction of action
parameter set 1

Positive (heating)

Direction of action
parameter set 2

Positive (heating)

Item no. 51240-5-9970 · ENU · Change 211950 · Approved 2020-09-21 · Page 8 / 13

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · info1@de.ebmpapst.com · www.ebmpapst.com

Summary of Contents for R3G250-AY11-C1

Page 1: ...lists are permitted to install the device to carry out a test run and to perform work on the electrical installation 1 3 Basic safety rules 1 1 3 Basic safety rules The safety hazards associated with...

Page 2: ...er equipment Verify that the entire setup is EMC compliant 1 7 Mechanical movement DANGER Rotating device Risk of injury to body parts coming into contact with the rotor or the impeller Secure the dev...

Page 3: ...use In particular operating the device in the following ways is prohibited and could be hazardous Operating the device in an unbalanced state e g due to dirt deposits or ice formation Resonant operat...

Page 4: ...essure tap k factor 70 not included in scope of delivery 2 Max clearance for screw 16 mm 3 Cable diameter min 4 mm max 10 mm tightening torque 2 5 0 4 Nm 4 Tightening torque 3 5 0 5 Nm Item no 51240 5...

Page 5: ...ned at optimum efficiency level The ErP data is determined using a motor impeller combination in a standardized measurement setup 3 4 Technical description Weight 6 4 kg Size 250 mm Motor size 84 Roto...

Page 6: ...tor that this device is only connected to a connection point with a Ssc value that is greater than or equal to 120 times the rated output of the arrangement 4 CONNECTION AND STARTUP 4 1 Mechanical con...

Page 7: ...ominal voltage Fuse Automatic circuit breaker Cable cross section Cable cross section VDE UL VDE mm AWG 3 PE AC 380 480 VAC 16 A 15 A C16A 1 5 2 5 16 AWG American Wire Gauge 4 2 3 Reactive currents Be...

Page 8: ...box if water is constantly present at the cable glands To prevent the constant accumulation of water at the cable glands the cable should be routed in a U shaped loop wherever possible If this is not...

Page 9: ...to 100 modulation level KL3 2 8 GND Reference ground for control interface SELV KL3 3 7 0 10 V Use control current sensor value input 0 10 VDC impedance 100 k only as alternative to 4 20 mA input SELV...

Page 10: ...supply Switching off the device for maintenance Switch off the device via the control input Do not switch the motor e g in cyclic operation on and off via power supply Disconnect the device from the...

Page 11: ...ect the operating point Let the device cool down To reset the error message switch off the line voltage for at least 25 s and then switch it on again Alternatively reset the error message by applying...

Page 12: ...mal bearing noise acoustic At least every 6 months Replace device 6 4 Disposal For ebm papst environmental protection and resource preservation are top priority corporate goals ebm papst operates an e...

Page 13: ...pose of electronic components employing the proper procedures for electronic scrap Please contact ebm papst for any other questions on disposal Item no 51240 5 9970 ENU Change 211950 Approved 2020 09...

Reviews: