8.3- Mounting the Boiler
After determination of boiler mounting location follow the instructions given below.
• The points of lock screws of wall bracket and assembly bracket are marked by using the assembly
template inside installation and user’s operating instructions of the device (pages 34-35-36).
• After drilling the marked points, wall assembly bracket and assembly bracket are fixed on the wall by
the dowel and lock screws which are inside the packaging of the device.
• Finally, the boiler is hanged on the wall by placing the assembly bracket on the back side of the boiler
on the mounting bracket assembled on the wall.
Figure 9
9- CONNECTIONS
9.1- C
o
ndensate Discharge C
o
nnec
�o
n
All condensing boilers generate condensing discharge. The amount of the
condensate water depends on the working conditions of your appliance. This
can be up to 1.7 litres condensate water per hour.
• The condensation water must be connected to a drain with the help of a plastic hose which is connect-
ed to the end of siphon. The use of standard discharge hose, which is given with boiler (50 cm), is
recommended for connection to the drain. The addition of 1 cable tie connection on the hose should be
made for fixing.
• If drain hose will be connected to drain outside of the building, insulation should be provided to prevent
freeze of hose.
• The condensate discharge hose and interconnection parts must be made of plastic material.
• All horizontal parts must be connected at a slight 2° or 3° downwards incline to ensure to a good flow.
Summary of Contents for CONFEO PREMIX P 14 HCH
Page 2: ......
Page 13: ...13 5 5 Electrical Diagram...
Page 16: ...16 Figure 6 7 3 Distances for Placement of Flues Figure 7...
Page 37: ...37 15 INSTALLATION TEMPLATE 15 1 HM Model...
Page 38: ...38 15 2 HCH Model...
Page 39: ...39 15 3 HST Model...
Page 43: ......
Page 45: ......
Page 46: ......