The EcoX installation
begins at the downhill
edge of the roof and
progresses uphill.
Installation is sequential
and requires minimal
hand tools.
Installation steps:
1. Layout Array on
rooftop.
2. Install Attachment
Kits to rooftop.
3. Install the Junction
Box Bracket.
4. Install Clamp
Assemblies on
downhill row.
5. Install the Skirts.
6. Install Couplings to
Skirts.
7. Install Modules
8. Install Clamps and
Couplings on uphill
side of Modules.
9. Level the row of
Modules.
10. Repeat Module
install on
subsequent rows.
11. Install additional
Bonding Clips at one
end of each row to
complete row to
row bonding.
Required Tools:
Tape Measure
Chalk Line
Hammer
Drill with 3/16" Bit
Flat Roofing Bar
Impact Driver
1/2" Socket
String Line
Torque Wrench
Chalk
l
l
l
l
l
l
l
l
l
l
Overview of Components
Note: Rooftop and shingles not shown for clarity
Attachment Kit
Clamp
Coupling
Coupling
Skirt
Adjoining
Skirts
Modules
(transparent for
visual clarity)
3 of 31
EcoX Gen2 Installation Guide, Rev 1.11
Summary of Contents for EcoX
Page 1: ...EcoX Gen2 Installation Guide Rev 1 11 Installation Guide Gen2 ...
Page 31: ...EcoX Gen2 Installation Guide Rev 1 11 26 of 31 11 Grounding and Bonding cont ...
Page 32: ...EcoX Gen2 Installation Guide Rev 1 11 27 of 31 11 Grounding and Bonding cont ...
Page 33: ...EcoX Gen2 Installation Guide Rev 1 11 28 of 31 11 Grounding and Bonding cont ...