- 10 -
While suspending the machine, crane cable must be tie to machine tightly, keeping the machine
horizontal.
disassemble the ground bolt in the pallet after the machine is well located, and take the pallet
aside
。
Fixation
Rubber gasket is recommended to reduce vibration and noise while rivet the bottom plate.
④
Water pipe connection
Heated water pipe must be packed with thermal isolation material to avoid thermal capacity loss or
dew dropping.
Inlet connection pipe must be equipped with a water filter.
The connection water pipes must be well matched (refer to specification parameters sheet).
PVC or PP-R pipe is recommended to use as water pipe.
Hot water pipe must be equipped with water pump
、
Soft tie-in
、
a water filter
、
One way valve
、
Flow meter
、
exhaust valve
、
Drain valve
、
Shutoff valve and so on
。
Heating pipe must be equipped with Soft tie-in
、
a water filter
、
One way valve
、
Flow meter
、
Drain
valve
、
Shutoff valve ,And then connected to underground inlet/outlet water pipe.
Drain cock should be installed at the highest point of hydraulic circle. After the hydraulic circle is
connected completely, exhaust air inside hydraulic circle.
Drain valve should be installed at the lowest point of water pipe.
Please note:
The appliance shall be installed in accordance with national wiring regulations.
Please make sure the following working conditions. the voltage can not be more or less than 10%
of rated voltage and the frequency can not be more or less than 1% of rated frequency. The height
above sea level should be less than 1,000 meters.
Working water temperature available from 8
~
50 , maximum water pressure 10 bar.
Wires must be connected according to the instruction of electrical connection diagram.
c r ane hook
c r ane c abl e
pr oec t i ng c hi pboar d
Summary of Contents for CAM-20XB