32
9.4 Boiler Start-up and Operational Test
Verify air is purged from hydronic piping
1.
System test pumps - verify each pump is
2.
operational
Verify gas piping
3.
Confi rm pressure test. See section 7.3.
•
Visually inspect piping to determine there are no
•
open fi ttings or ends, and all valves at unused
outlets are closed and plugged/capped.
Purge air from piping
•
Check piping and connections for leaks
•
immediately after gas is turned on. Shut off
gas supply and make necessary repairs if leaks
found.
Follow OPERATING INSTRUCTIONS to initiate boiler
4.
operation. See section 10.
Inspect combustion air and vent piping. Verify pipe
5.
is not leaking and terminations are unobstructed
and vent gas discharge is not a nuisance or hazard.
Verify boiler functions.
6.
Inspect condensate disposal system. Verify
7.
condensate fl ows adequately and is disposed
properly.
Check control module operation.
8.
Check fi eld-sourced limits, low water cutoffs, etc.
9.
per manufacturer's instructions.
9.5 Check Combustion
Natural Gas
Measure input. English units*
1.
Turn off gas to all other appliances.
•
Use ½, 1 or 2 cu ft dial on gas meter. Measure
•
time required for one or more complete
revolutions. Measure time for 1-2 minutes.
Calculate input.
•
Input (MBH)
=
3600 x cu ft
seconds
Example: Gas fl ow from
Meter = 2 cu ft
Measured time = 72 seconds
Rate (MBH)
=
3600 x 2 cu ft
=
100 MBH
72 seconds
*Metric - See Glossary
9 - START UP PROCEDURE
Compare to boiler rating
2.
Size
Minimum
Maximum
075
65
85
100
90.0
110
Adjust rate if needed using diagram 9-3 below.
3.
NOTICE
Contact ECR Technical Support @ 800-325-5479 for
additional information or assistance.
Check CO
4.
2
. Natural gas should be between 8.5%
and 10.0%. See Figure 9-4 Combustion air analyzer
port.
If CO
•
2
is low increase gas fl ow following fi gure
9-3.
If CO
•
2
is high decrease gas following fi gure 9-3.
Propane Gas
Most propane systems do not have fl ow meters.
Check CO
1.
2
. Propane should be between 9.5% and
11.0%.
If CO
•
2
is low increase gas fl ow following fi gure
9-3.
If CO
•
2
is high decrease gas fl ow following fi gure
9-3.
OUT
MIN
1/4" FLAT HEAD
SCREWDRIVER
To increase gas fl ow turn 'throttle' left or counter
•
clockwise
.
To decrease gas fl ow turn 'throttle' right or
•
clockwise
.
Limit adjustment to one turn and retest.
•
9-3 Gas Valve
Summary of Contents for 075 97gb
Page 56: ...56 14 WIRING DIAGRAM 14 1 Connection Diagram ...
Page 57: ...57 14 WIRING DIAGRAM 14 2 Schematic Diagram of Ladder Form ...
Page 73: ...73 ...
Page 74: ...74 ...
Page 75: ...75 ...