Commissioning
If connections are no longer accessible after system
installation, connect all cables before final mounting. If
necessary, also insert the MicroSD card and the MicroSIM
card in advance.
Only connect the power cable when the power supply is
switched off.
Only insert the MicroSIM card when the system is switched
off. Only remove the MicroSIM card when the system is
switched off.
Before commissioning, we recommend connecting or inserting:
•
Monitor
•
USB keyboard and mouse
•
Network cable (optional)
•
MicroSD card and MicroSIM card (optional)
•
DC power supply
Other plug & play devices can be connected after commissioning.
Switching on the device / Operation
After all preparations have been made, the system is ready to be connected
to the power supply.
Press the power button to switch on the system. When the system is
powered, the Power LED on the optional power button will be on. When the
system boots, the Status LED on the housing lights up to indicate that all
internal voltages are at normal levels.
If an operating system is installed, it will start now. An operating system
installation can be performed with all common installation media such as
USB stick, USB DVD drive or remote network start. The BIOS boot order
has to be adjusted accordingly. To enter the BIOS setup, press the "Del" key
immediately after switching on.
Please refer to the operating system manual for switching off / shutting down.