26
Installation manual
Place the washer extractor so that it is easy for the user and the service technician to do their work.
Leave at least 1 m (40″) (according to the recommendation in standard EN 60204) between the machine, a wall or
any other machine at the sides.
11.3 Installing the shock absorber runners
Preparation of the ground and the machine.
• Carefully degrease the ground and the machine’s base plates.
Positioning the shock absorber runners.
• Place each shock absorber runner (P) at its respective location (see diagram) raising each of the machine’s sup-
port points in series and taking care to let the runner inside of the base plates.
Commissioning the machine
• Time: before commissioning the machine, each support point must be embedded by being crushed in by the run-
ner’s upper layer and the lower layer must have been pushed into the porosity in the ground.
The crushing time is 2 hours at an ambient temperature of 18 °C.
Warning
Electrical safety device.
As rubber is a very good electric insulating material, the earthing of the machine is compulsory.
Moving machines sealed with the shock absorber runners
• Moving machines sealed with the shock absorber runners
11.4 Instructions for securing the machine on the ground
Caution
Only for machines without weighing equipment.
Place the machine on a perfectly even surface and horizontal.
Control this using a water level (see drawing).
Each point must be level.
Summary of Contents for WHB5 500H
Page 2: ......
Page 4: ......
Page 21: ...Installation manual 21 Back view Right view Drain connection Top view ...
Page 42: ...42 Installation manual ...
Page 45: ......