T 3000 - T 3500
19
Empty conduits
Use separate conduits for the power line and the control leads.
Use an additional (separate) conduit for each induction loop.
The distance between the conduits should be as large as possible.
Drawing 5
Requirements regarding the foundation
A minimum concrete strength class of C20/25 (or higher)
The use of heavy duty anchor bolts (M12).
Observe the foundation dimensions quoted in this manual. The installation
distance between the barrier housing and the foundation edge has to be
approx. 100mm.
WARNING!
Risk of injury by insufficient fastening!
Tilting barrier housings can result in severe injuries.
Before installation ensure a safe stand of the barrier housing.
Do not lean the barrier boom against a wall or similar before installation.
Store the boom horizontally only.
Install the barrier housing as specified.
Use the recommended heavy duty anchor bolts M12, at least M10 is
required.
During maintenance check the housing for correct fastening on the
foundation.
Summary of Contents for T 3000
Page 12: ...T 3000 T 3500 11 4 Declaration of incorporation Drawing 2...
Page 18: ...T 3000 T 3500 17 7 2 Mounting dimensions Drawing 3...
Page 34: ...T 3000 T 3500 33 8 4 Circuit diagram Drawing 21...
Page 35: ...T 3000 T 3500 34 Drawing 22...
Page 36: ...T 3000 T 3500 35 Drawing 23...
Page 37: ...T 3000 T 3500 36 Drawing 24...
Page 38: ...T 3000 T 3500 37 Drawing 25...
Page 39: ...T 3000 T 3500 38 Drawing 26...
Page 40: ...T 3000 T 3500 39 Drawing 27...
Page 42: ...T 3000 T 3500 41 10 Layout exploded drawing Drawing 28...