Initial operation
18
BA_Elmasonic S_EN_Vers. 05.2019
© Elma Schmidbauer GmbH
5
Initial operation
Please keep the original packing or dispose of it according to
the relevant waste disposal regulations. You can also return the
packing to the manufacturer free destination (to your account).
The machine must only be sent in the original packaging for
transport (e.g. in the case of service).
Check the Elmasonic S for possible transport damages before
initial operation. In case of visible damage do not connect the
unit to the mains. Contact your supplier and forwarding agent.
For operation, place the unit on a dry and solid surface. Ensure
that the workplace is sufficiently ventilated!
Do not use a soft surface (e.g. a carpet) as this may impede the
ventilation of the unit.
Risk of electrocution due to humidity inside the unit!
Protect the unit from entering humidity.
The unit inside is splash-water-proof. Keep workplace and
casing dry in order to prevent electrical accidents and damages
on the unit.
Allowed ambient temperature during operation:
+5°C - +40°C
Allowed relative humidity of air during operation: max. 80%
In-door operation only
5.1
Set up of the liquid drain (S 30
– S 900 H)
On the delivered unit, the drain duct for the cleaning liquid is
closed off with a plastic screw cap.
For setting up the liquid drain fix the delivered tube socket to
the drain duct.
1. Unscrew (clockwise) the plastic screw cap
(see illustration
5.1)
2. Screw the tube socket (included in delivery) onto the inside
thread of the drain duct (clockwise).
3. Turn the tube socket into the required drain position
(see
illustration 5.2)
.
The plastic thread is self-sealing when the socket has been
screwed in by hand as far as possible.
Note:
Unscrewing the tube socket (anti-clockwise) can
cause a leak of the thread.
Packing
Check for transport
damages
Placement
DANGER
Ambient conditions
Proceed as follows