Step 6:
Place the gasket into position on the foundation pad so that the gasket
will lie underneath the bottom of the cabinet when it is placed. The
gasket should lie so the cutouts are in position around the conduit
openings, and over the anchor bolts.
Step 7:
The front chamber door must stay open and the wind latch secured.
Step 8:
Remove the cable cone from the cabinet floor by removing the 1/4"
hardware (Fig. 7). Remove and set the cable cone safely aside for later
reattachment.
Step 9:
If the cabinet will be equipped with cables from a remote location,
remove the cable cone from the cable sleeves in the protection chamber.
Set the cable cone safely aside for later reattachment.
4.4 Lifting the Cabinet
DAN
G
ER
Improper hoisting equipment and unsafe lifting procedures can result in serious
injury or death.
•
Observe the following safety measures, as well as all local safety proce-
dures, when performing the tasks in this section.
•
Keep the equipment and the cabinet away from any power lines.
•
Keep bystanders away from work operations at all times.
Fig. 6 : Gasket Placement
OSP
CABLE
ENTRY