Installation Manual
21
Wiring
Figure 3-7: Shielded heat shrink covering exposed drain wires
g. Position gland clamping insert so the interior end is flush with the heat shrink.
h. Fold the cloth shield or braid and drain wires over the clamping insert and
approximately 1/8 inch (3 mm) past the O-ring. See
Figure 3-8
.
Figure 3-8: Folded cloth
i. Install the gland body into the core processor housing conduit opening. See
Figure
3-9
.
Figure 3-9: Installing the gland body
7. Insert the wires through the gland body and assemble the gland by tightening the
gland nut.
8. Identify the wires in the 4-wire cable.
Use the 4-wire cable supplied by Micro Motion. This cable consists of one pair of 18
AWG (0,75 mm
2
) wires (red and black) for the VDC connection, and one pair of 22
AWG (0,35 mm
2
) wire (green and white) for the RS-485 connection.
9. Connect the four wires to the numbered slots on the core processor. See
Figure 3-10
.