Page 28
36776-4-0117
1. Insert fireplace into enclosure.
2. Level fireplace.
3. Secure three middle mounting brackets with drywall screws
to the framed opening above the fireplace as shown in
Figure 43.
Notice: The drywall screws are located in the instruction
envelope packet. Secure fireplace on left and right through
side nailing flanges.
4. Install the fireplace cabinet face flush with the wall-board,
secure the nailing flanges at the top and sides of the
fireplace with a 1/2-inch setback. This allows you to use the
supplied non-combustible board above the fireplace.
5. Check gas lines for leaks.
6 Plug AC adapter and LED transformer to junction box.
7. Install the wall-mounted control box within 10 feet of the
center of the fireplace.
(See Figure 43)
WALL MOUNT
CONTROL BOX
10 FEET
MAX
SCREW INTO
EACH BRACKET
6” MIN
CENTER
OF
FIREPLACE
Figure 43
8.
Install a plastic bushing in both the liner and outer walls of
the fireplace. (See Figure 44 & 45)
Figure 44
Figure 45
9. Route the yellow LED wire harness, grey remote receiver
harness,and red/black battery backup harness through the
bushings to the wall mount controls and connect.
(See Figure 46)
REMOTE
SWITCH
COVER PLATE
YEL/BLACK
GRAY EXTENSION
WIRE
YELLOW EXTENSION
WIRE
RED/BLACK
TO FIREPLACE
TO FIREPLACE
Figure 46
10. Set receiver in wall box to remote. Set switch on side of heat
shield to intermediate pilot (up).
*If switch is in "standing pilot" (down position, the pilot will ignite
automatically when power to the fireplace is turned on .
FIREPLACE & NONCOMBUSTIBLE BOARD
INSTALLATION - FLUSH MOUNT
Summary of Contents for Boulevard VFLL60FP90LN-1