28365-2-0811
Page 29
NOTE:
Termination cap should pass through the wall firestop from
the exterior of the building. Adjust the termination cap to
its final exterior position on the building.
WARNING
: Termination cap must be positioned so that arrow
is pointing up.
Attach the termination cap with the four wood screws provided.
Before attachment of the termination, run a bead of silicone sealant
rated above 250°F on its outside edge too, so as to make a seal
to the exterior wall.
NOTE
:
Wood screws can and should be replaced with appropriate
fasteners for use on stucco, brick, concrete or other types
of siding.
CAUTION
:
If exterior walls are finished with vinyl siding (or materials
that could become discolored or warp), it is necessary to install a
vinyl siding standoff.
The vinyl siding standoff will be installed between the vent termination
and the exterior wall. (See Figure 44) This horizontal vent termination
bolts onto the flat portion of the vinyl siding standoff, so an air space
will exist between the wall and the termination cap.
Figure 44
For installations requiring a vertical rise on the exterior of the
building, 14-inch and 36-inch tall Snorkel Terminations, as shown in
Figure 45 are available. Follow the same installation procedures as
used for standard Horizontal Terminations. If the Snorkel Termination
must be installed below grade, (i.e. basement application), proper
drainage must be provided to prevent water from entering the
Snorkel Termination. Refer to Figure 46. Do not attempt to enclose
the Snorkel within the wall or any other type of enclosure.
12 INCHES
MINIMUM
SNORKEL
12 INCHES
MINIMUM
ADEQUATE
DRAINAGE
SNORKEL
Figure 45
Figure 46
HORIZONTAL TERMINATION