26988-3-1012
Page 38
FOR FIREPLACE MODEL: ADVD32FP34N, USE CONVERSION KIT PART NUMbER 19553 (Included with Fireplace)
FOR FIREPLACE MODEL: ADVD36FP34N, USE CONVERSION KIT PART NUMbER 19554 (Included with Fireplace)
1. If fireplace is installed, turn OFF gas and electric supply to
fireplace before making gas conversion.
2. Remove top louver, grasp louver, lift and pull forward.
3. Lower bottom louver, lift and hinge forward to remove.
4. Release two glass frame spring clamps at bottom of firebox
and remove glass door assembly.
5. Remove logs from burner assembly.
6. Remove one (1) 8x¼" screw from air shutter. (Located at the
left rear of burner.)
7. Located to the right of the pilot is a burner hold-down tab,
using a pliers, bend burner hold-down tab away from the
main burner.
8. Remove main burner by pivoting main burner up and
forward, then slide main burner from left to right. Be careful
as you remove main burner in order to protect the pilot from
being damaged.
9. Remove (unscrew) the air shutter from orifice fitting.
10. Remove (unscrew) the Natural gas main burner orifice from
orifice fitting.
11. Install Propane(LP) gas main burner orifice into orifice fitting:
for ADVD32
ORIFICE MARKED 56
for ADVD36
ORIFICE MARKED 55
12. Replace air shutter onto orifice fitting. Air shutter must be
threaded and bottomed-out onto orifice fitting.
13. Replace main burner onto burner assembly. Slide main
burner from right to left into left end burner locator, pivot
main burner away from you and reconnect burner into air
shutter.
14. Adjust air shutter setting to:
1/4" OPEN
on ADVD32 and
ADVD36, then secure the air shutter to main burner with one
(1) 8¼" screw from Step 6.
15. To convert pilot orifice, pull top of pilot hood off to expose
orifice.
16. Remove Natural gas pilot orifice from pilot burner with a
properly sized Hex wrench.
17. Insert
Appropriate propane (LP) gas pilot orifice
into pilot
burner and secure.
18. Replace pilot hood to pilot assembly.
19. Convert gas valve as instructed in
S.I.T. Propane(LP) gas
valve conversion kit.
20. The converted fireplace must be connected to a supply of
the conversion gas and checked for leaks at all connections.
21. Refer to Log and Ember Placement in your Installation
Instructions and Owner's Manual to replace logs onto burner
assembly.
22. The fireplace must be checked to ensure it is operating
at the correct pressure of 10.0" w.c.The Air Shutter may
require minor adjustment to produce light yellow rear flame
appearance. Replace ember material over front burner parts.
23. Replace glass onto firebox.
24. Secure the two glass frame spring clamps at bottom of
firebox.
25.
Fill out the gas conversion label with date converted
and installer name. Then affix label near valve on inner
bottom of fireplace.
26. Align the tabs on top louver brackets with slots in front posts
to secure top louver.
27. Close bottom louver. Lift slightly to engage the end tabs into
the slots in fireplace sides to close bottom louver.
28. Gas conversion is completed.
verifying Input Rate of Converted Fireplace
The input of the fireplace must be checked as follows:
1. Turn off all other gas appliances. Clock the gas meter and
determine the number of seconds required to consume one
cubic foot of gas.
2. 3600 ÷ time ( in seconds) = cu. Ft. per hour.
3. Then cu. Ft. per hour x heating value of gas = input rate
(Btuh). On installation without gas meters, check manifold
for proper pressure.
Note
: The main burner flame and pilot burner flame must be checked for proper flame characteristics, as outlined in the Installation
Instructions and Owner's Manual.
If fireplace is not installed or warranty card has not been returned to Empire Comfort System's, Inc., check off type of gas converted to
on card. Also, indicated conversion by adding "Conv." behind type of gas.
INSTRUCTIONS FOR CONvERSION
GAS CONvERSION INSTRUCTIONS (continued)