DEVICE CONFIGURATION
smart Econ - emz-HCW - 180116
115
• Select ›PUMP SETTINGS‹.
• Change the parameters if necessary.
- ›stop delay time (sec)‹
- ›switch on delay (min)‹
- ›SET MIN TEMP HG 1‹ - ›limit value‹: Minimum temperature of the heat generator as buffer dis-
charge protection
Configure heat pump
(Only for systems with heat pump)
• Select ›HEAT PUMP‹ from the ›COMMISSIONING‹ menu.
• Change the name of the heat pump if necessary.
• Change other parameters if necessary.
- ›minimum supply temp. (°C)‹: The pump stops at temperatures below the set value (startup pro-
tection). Recommendation:<10°C
PUMP SETTINGS
^
stop delay time (sec)
30
sw itch on delay (min)
0
SET MIN TEMP HG 1
BACK
i
HEAT PUMP
^
NAME
Heat Pump
current set point (°C)
0
supply temp boiler load (°C)
60
minimum supply temp. (°C)
0
maximum supply temp. (°C)
60
hysteresis (K)
4
supply temp. above mixer (K)
2
sw itch on delay (min)
1
i
PUMP SETTINGS
BACK