Commissioning
Fieldgate PAM SFG600
18
Hauser
HART module with Siemens ET200SP IM 155-6PN HF
HART module
Firmware Version
Module 4xI 2-wire HART
Order code: 6ES7 134-6TD00-0CA1
V1.0.0
V1.0.1
9
Commissioning
Follow the sequence indicated when commissioning the Fieldgate PAM SFG600 in order
to avoid errors when establishing the connection. The Ethernet cables must be connected
to the configured PROFINET segment of the plant that is in operation.
1. Insert the ETH1 Ethernet cable (PROFINET).
2. Insert the ETH2 Ethernet cable (Fieldgate PAM SFG600).
3. Connect the power supply.
The Fieldgate PAM SFG600 starts scanning the network automatically.
The plant can be configured via the Field Xpert SMT70 tablet PC.
The scan can take up to several hours.
At least one Field Xpert SMT70 tablet PC must be configured as the gateway with the IP
address of the "ETH2 PAM Client" connection. The HART devices must have unique TAGs,
and the PROFINET controller must be in operation. The "ETH1 PROFINET" connection,
configured with a free PROFINET IP address, must be connected to a free port of a
PROFINET switch.