Commissioning
Proline Promag 51
56
Hauser
6.2
Function check
Make sure that all final checks have been completed before you start up your measuring point:
• Checklist for "Post-installation check"
• Checklist for "Post-connection check"
6.3
Switching on the measuring device
Once the connection checks have been successfully completed, it is time to switch on the power
supply. The device is now operational. The measuring device performs a number of post switch-on
self-tests. As this procedure progresses the following sequence of messages appears on the local
display:
Normal measuring mode commences as soon as start-up completes.
Various measured-value and/or status variables (HOME position) appear on the display.
!
Note!
• If start-up fails, an error message indicating the cause is displayed.
• If a device is in the custody transfer mode, the error message "POWER BRK. DWN" appears on
the display each time the power supply is applied. This error message has to be reset and
acknowledged via the status input. Each time an error is reset, a display test is triggered.
PROMAG 51
START UP . .
Start-up message
Æ
DEVICE SOFTWARE
V XX.XX.XX
Current software version (example)
Æ
CUSTODY TRANSFER
NO / YES
Status display of the custody transfer mode
YES = in custody transfer mode, NO = not in custody
transfer mode
Æ
SYSTEM OK
OPERATION
Beginning of normal measuring mode
Æ