IMPORTANT!
READ AND FOLLOW
ALL
INSTALLATION AND MAINTENANCE INSTRUCTIONS, INCLUDING
CLEANING THE UNIT AS SPECIFIED, AND REPLACING GASKETS ANNUALLY, AND PARTS AS NEEDED.
ENGLAND’S STOVE WORKS IS NOT RESPONSIBLE FOR ANY DAMAGE OR INJURY INCURRED DUE TO NEGLECT, OR
DUE TO UNSAFE INSTALLATION OR USAGE OF THIS PRODUCT. CALL TECHNICAL SUPPORT WITH ANY QUESTIONS.
10
FLOOR AND WALL PROTECTION
Floor Protection
If your floor is constructed of a non-combustible material such as brick or concrete, there is no need
for floor protection. If the floor is constructed of a combustible material such as hardwood, linoleum, or
carpet, then you will be required to use floor protection between the unit and the combustible. The
protection should be U.L. approved or equivalent (ULC if Canada) and must be large enough to provide a
minimum of one inch (1.0”) behind, four inches (4.0”) on both sides of the stove and at least six inches
(6.0”) in the front of the unit. This floor protection is intended as spark and ember protection only,
therefore it need only be noncombustible (there is no required R value).
Wall Protection
From the rear and the sides of this stove only six inches (6”) of clearance is required to paneling, wallpaper
or drywall. The pellet vent pipe usually requires the standard three inches (3”) of clearance, or as
recommended by the manufacturer. Normally additional wall protection is not required with this type unit.
1.
If 3” flue pipe exceeds 15’ in length, increase to 4” flue pipe for remaining flue connections.
2.
Total flue length should not exceed 35’.
3.
Horizontal run not to exceed 4’.
4.
Floor protector must extend 6” from front of unit, 4” from sides and 1” from rear.
5.
If the total run of outside air connection exceeds 6’, if more than 2 elbows are used, or if a
basement install, use 3” metal pipe (and coupler) instead.
6.
Outside Air is mandatory for proper safe operation.
Masonry Connection
Illustration 1
Freestanding Pellet Installation
Caution: Follow the pipe manufacturer’s installation instructions and directions for
passing through combustible walls and ceilings. Check local codes in your area.
Our Part AC-3000 is
acceptable for
through-the-wall
installation;
AC-3100 for 4000+
ft. installations.
(AC-33000 or AC-
33100 if Canada)
Must have minimum
3” adapter before tee
for longer run.
For shorter run
(such as Masonry
Connection below),
tee alone is
acceptable.
Basement Installation should
be performed by
professional installer. Use
3” metal pipe and coupler
for Outside Combustion Air.
Minimum 3 feet (3’)
clearance from ground to the
Pellet Vent Exhaust Pipe.
INSTALL VENT AT CLEARANCES SPECIFIED BY THE VENT MANUFACTURER.
Summary of Contents for 25-PDVC