Code: I.H4.V10.3003
Installation and Maintenance Manual
Version: 07
15 / 66
Ennera Energy and Mobility, S.L.
This document contains confidential information which is property of Ennera Energy and Mobility, S.L. The copy, transmission or use by other people, of the whole document or
part of its contents, is not allowed without written permission from Ennera Energy and Mobility S.L.
10.
Insert the third tower section over
the second section:
•
Ensure that the weld seam of the
new section is aligned with the
previous section.
•
Pass the guide through the third
section.
•
With tape, mark the interference
distance. In this case, at 470mm
from the edge.
•
Apply some grease or oil over the
lower up section (interference area).
•
Fit manually 2nd and 3rd sections.
11.
Adjust both sections until in-
terference distance mark is reached by
the third section (follow step 9).
12.
Insert the fourth section over the
third section. To do this:
•
Ensure that the weld seam of the
new section is aligned with the
previous section.
•
Pass the cable guide through the
fourth section.
•
With tape, mark the interference
distance. In this case, at 400mm
from the edge.
•
Apply some grease or oil over the
lower up section (interference area).
•
Fit manually third and fourth
sections.
The eyebolt of the fourth
section should be pointing
up as shown in the picture.
470mm
Second section
Third section
T1
T2
T3
T4
400mm