Connect the tower shackle (W18) to
the tower’s fourth section (T4) eyebolt.
Connect also the elevation cable (W17).
10.
Connect the other shackles (EL-4) to
the ground anchor (EL-1) eye and the
ginpole (EL-6) end.
11.
Connect the tractel (EL-3) to the
ground anchor (EL-1) eyebolt.
12.
Insert the tractel cable trough it and
connect the other side to the top
eyebolt of the ginpole.
13.
Use the tractel (EL-3) in lift up mode
as shown in the figure to lift the ginpole
(EL-6) up around 1 m from the tower.
Be careful during the lifting
up process. No operators
around the ginpole and
tower while this is lifting.
If anytime the tower needs
to be lifted down during
the process, change the
helping rod of the tractel
and work in the same way
as lifting up.
W17
W16
T4
EL-1
EL-4
EL-6
EL-3
EL-1