5.
INSTALLATION
5.1.
Foundation
See drawing JI.H4.V10.4000 (Annex 4)
for foundation construction details.
The foundation must be
done at least 3 weeks
before wind turbine
installation.
1.
Make a hole of 2x2m and 1m depth.
2.
If the soil is not consistent, make a
box of wood to sustain the walls of the
hole.