Code: I.H4.V10.3003
Installation and Maintenance Manual
Version: 07
9 / 66
Ennera Energy and Mobility, S.L.
This document contains confidential information which is property of Ennera Energy and Mobility, S.L. The copy, transmission or use by other people, of the whole document or
part of its contents, is not allowed without written permission from Ennera Energy and Mobility S.L.
3.
Add a 75mm of thick plain cement
concrete layer.
4.
Place the foundation reinforcement
steel bars inside the hole, fixing the bars
between them with metallic wire (up
and bottom).
Lower reinforcement at a
distance of 100mm from
plain cement concrete.
5.
Attach an earthing cable of 6mm
2
to
the bottom part of the reinforcement
bars.
(Foundation earthing
cable not supplied.
Length = 2m)
6.
Place the 8xM30 fixing steel bolts
(FD-1) with the template (FD-2), so that
the 8 bars are perfectly vertical and
concentrically to tower axis.
Follow dimension of the
drawing “Bolts position
tooling” in Annex 4.
2 bolts must be aligned
with the lifting direction.
After placing the template, level it.
lifting direction
FD-1
FD-2