Setting Up the 5C105
3-2
5C105 Setup
4. Remove the accessory package.
5. Remove the Electrostatic Discharge (ESD) Wrist Strap package.
6. Remove the Console Cable Kit and set aside. This kit will be needed to set up the modules for
the 5C105 through Local Management.
3.2
SETTING UP THE 5C105
The following sections describe the procedures that must be followed to complete the installation
of the 5C105.
3.2.1
Installation
Once a suitable site has been chosen, the 5C105 can be installed. The chassis can be freestanding
or rack mounted.
It is recommended that the 5C105 installation proceed in this order:
1. Install the cable management bar.
2. Mount the chassis to a 19-inch rack or other secure location.
3. Attach the Electrostatic Discharge Wrist Strap.
4. Install the Power Supply Module(s).
5. Install the Interface Modules.