If the state grid cannot match the following situations (table 5.3.1), it bring the Envertech 

EnverBridge to the rest mode. 

Checklist
Check the mechanical and electrical installation of the unit before startup. Go through 
the checklist below together with another person. Read the Safety instructions and EC 
directives on the previous pages of this manual before you work on the unit.

Mechanical Installation
Check screw connections on the EnverBridge for tightness. The ambient operating 

conditions  are  allowed.  (See  Technical  parameter);  The  unit  is  fixed  properly  on  a 
nonflammable wall or the combiner box or the rack. (See Mechanical installation.) The 
cooling air will flow freely. The unit is fixed tightly and support is enough. (See Mechani

-

cal installation.)  

Electrical Installation
Check all screws of the connection terminals in the installation system before and after 
the EnverBridge for tightness. 

The AC input voltage matches the unit nominal voltage.  Assure EnverBridge AC cable’s 

connections and their tightening torques are OK. There are no tools, foreign objects or 
dust from drilling inside the unit. Unit, connection box and other covers are in place. The 
Ethernet cable connections are OK.  The external cords and cables are fixed tightly, and 
strain relief clamp is provided for external accessible cords and cables. Cord and cable 

inlets are sealed completely after cord/cable installation. 

The device has been checked at the factory and adjusted so that it can be commissioned 
immediately after being installed. 

Following Section Installation checklist, for your personal safety and to avoid damage, 
the following safety checks should be performed before start by a qualified person who 
has adequate training, knowledge, and practical experience to perform these tests. The 
data should be recorded in an equipment log. If the device is not operating properly or 
fails any test, the device has to be repaired.

1.Inspect the equipment and accessories for mechanical and functional damage. 
2.Inspect the safety relevant labels for legibility. 
3.Inspect the fuse to verify compliance with rated current and breaking characteristics. 
4.Measurement of insulation resistance 
5.Measurement of earth resistance 
6.Mounting structures: Verify tightness and integrity of bolts and other fastening 
devices, also check if there is significant corrosion.

The purpose of the manual for LCD of EnverBridge is to help users to know the function 
quickly and guide them to use LCD to perform how it works.

Monitoring the system and Showing the real-time working status
Helping installation personnel to confirm the system operation status
Making the system failure checking up more convenient for the maintenance and 
debugging personnel

The  start-up  logo  shows  on  the  LCD  screen  interface  once  the  power  of  EnverBridge 

equipment is on and starts to work. The first line shows the company name Envertech 

and the second line shows the company website www.envertec.com (as shown below).

6 LCD Abstracts

5.3 Grid Disconnect

11

12

WARNING 
Connect the EnverBridge to the electrical utility 
grid only after receiving prior approval from the 
utility company. 

WARNING 
Only qualified personnel could connect 
Envertech EnverBridge to the electrical utility 
grid.

Type

Voltage

Frequency

Rated

230V
50Hz

Variation Range

205V - 265V

47Hz – 51Hz

Table 5.3.1 Parameter of European state power grid

Start EnverBridge after checking all below steps:

5.4 Installation checklist

To ensure the safe operation of the devices, they may be installed and commissioned only 
by qualified personnel in full compliance with the warnings referred to in this manual.

5.5 Start-Up– Checks

6.1Brief introduction

6.1.1 Function of LCD

6.2 LCD 1602 interface
6.2.1Start-up interface

Summary of Contents for EnverBridge

Page 1: ...er Operating Manual Model Number EnverBridge This manual is an integral part of the unit Please read the instruction manual carefully before installation operation or maintenance Keep this instruction...

Page 2: ...id Connection 5 3 Grid Disconnect 5 4 Installation checklist 5 5 Start Up Checks 6 LCD Abstracts 6 1 Brief introduction 6 1 1 Function of LCD 6 2 LCD 1602 interface 6 2 1 Start up interface 6 3 Monito...

Page 3: ...ruction DANGER The DANGER symbols in this manual and on the EnverBridge Indicate a hazard with a high level of risk which if not avoided will result in death or serious injury CAUTION The CAUTION symb...

Page 4: ...not respond for any quality assurance and other risks For Envertech EnverBridge Warranty Terms and Conditions see the appendix of this manual 3 4 PV PCS _ Caution risk of electric shock CE mark is at...

Page 5: ...t installed environments suitable for it s IP rating CAUTION The device is intended for fixed installation Located on a part that is not removable without impairing the operation of the unit CAUTION V...

Page 6: ...07mm 3W 700g Natural convection no fans 40 65 IP65 CE 5 Years 7 8 Use the Power Line Carrier Communication PLCC technology within Photovoltaic power plant By PLCC technology EnverBridge collects gener...

Page 7: ...inverter array is exported to the utility grid Fault If the system does not operate correctly Envertech EnverBridge will stop automatically and enter into Disable mode The Envertech EnverBridge syste...

Page 8: ...these tests The data should be recorded in an equipment log If the device is not operating properly or fails any test the device has to be repaired 1 Inspect the equipment and accessories for mechanic...

Page 9: ...168 0 201 indicates a normal network connection and 192 160 0 254 indicates an abnormal network connection The figure of power efficiency which shows at the beginning of the second line indicates the...

Page 10: ...e the EnverBridge from the system Only trained and authorized professional personnel WHO ARE FAMILIAR WITH THE REQUIREMENTS OF SAFETY is allowed to perform servicing and maintenance work 6 5 Applicati...

Page 11: ...nverBridge Wear gloves and safety glasses Disconnect the EnverBridge from the Grid Isolating device Clean the EnverBridge with wet cloth carefully Introduction Use the monitoring website EnverPortal d...

Page 12: ...ill the EnverBridge serial Number in the blank space for example 90000001 click OK and finish the registration 19 20 9 Contact Zhejiang Envertech Corporation Ltd Tel 86 579 8926 6326 Email info envert...

Reviews: