FORM ET115.24-NOM4 (819)
SECTION 4 - INSPECTION, INSTALLATION & START-UP CHECKLIST
SECTION 4 - INSPECTION, INSTALLATION & START-UP CHECKLIST
RECEIVING & INSPECTION
DATE:
BY:
Unit Received Undamaged
__________
_________
Unit Received Complete As Ordered
__________
_________
Unit Arrangement Correct
__________
__________
Unit Structural Support Complete & Correct
__________
_________
HANDLING & INSTALLATION
Unit Mounted Level & Square
__________
_________
Proper Access Provided For Unit & Accessories
__________
_________
Proper Electrical Service Provided
__________
_________
Proper Overcurrent Protection Provided
__________
_________
Proper Service Switch/Disconnect Provided
__________
_________
Proper Chilled Water Line Size To Unit
__________
_________
Proper Hot Water Line To Unit
__________
_________
All Services To Unit In Code Compliance
__________
_________
All Shipping Screws & Braces Removed
__________
_________
COOLING/HEATING CONNECTIONS
Protect Valve Package Components From Heat
__________
_________
Mount Valve Packages
__________
_________
Connect Field Piping To Unit
__________
_________
Pressure Test All Piping For Leaks
__________
_________
Install Drain Line & Traps As Required
__________
_________
Insulate All Piping As Required
__________
_________
DUCTWORK CONNECTIONS
Install Ductwork, Fittings & Grilles As Required
__________
_________
Proper Supply & Return Grille Type & Size Used
__________
_________
Control Outside Air For Freeze Protection
__________
_________
Insulate All Ductwork As Required
__________
_________
ELECTRICAL CONNECTIONS
Refer To Unit Wiring Diagram
__________
_________
Connect Incoming Power Service or Services
__________
_________
Electrical Service of Correct Voltage and Ampacityto
Support Unit Operating Loads
__________
_________
All Field Wiring Installed With Code Compliance
__________
_________
Check All Wiring For Secure Connections
__________
_________
Summary of Contents for VHA
Page 10: ...ENVIRO TEC 10 FORM ET115 24 NOM4 819 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 41: ...ENVIRO TEC 41 SECTION 2 START UP FORM ET115 24 NOM4 819 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 54: ...ENVIRO TEC 54 FORM ET115 24 NOM4 819 SECTION 6 Dimensional Data 74 80083 ...
Page 78: ...ENVIRO TEC 78 FORM ET115 24 NOM4 819 SECTION 6 Dimensional Data NOTES ...