Maintenance 6. Joint #2
C12 Rev.3
203
8.
After fixing the Arm #2, fix the Arm #1 side arm.
Hexagon socket head cap bolts: 8-M6
×
25 (with a plain washer)
Tightening torque: 18.0
±
0.9 N·m
9.
Install the Joint #2 pulley 2 to the Joint #2 shaft.
Hexagon socket head cap bolts: 2-M5×10
(with a brass washer)
Tightening torque: 3.9
±
0.2 N·m
Set the key to the shaft and insert the pulley 2 while aligning to the key groove. The brass bushing
is not necessary for the screw for the flat surface. Set the bushing to the other screw and then fix
the screw.
If the screw positions are incorrect or the bushing is not set, it may cause damage on the side of the
brake and may result in the part being unable to be removed.
10.
Install the battery box.
Countersunk screws: 2-M3
×
8
Tightening torque: 0.45
±
0.1 N·m
11.
Install the following parts.
Battery
Battery board
Battery connector
For details, refer to
Maintenance 11.2 Replacing the Battery Board
, Installation steps (2) to (5).
12.
Install the Joint #2 timing belt.
For details, refer to
Maintenance 6.3 Joint #2 – Replacing the Timing Belt
, Installation steps (1) to (2).
NOTE
Summary of Contents for C12 Series
Page 1: ...Rev 3 EM204R4255F 6 Axis Robots C12 series MANIPULATOR MANUAL ...
Page 2: ...Manipulator manual C12 series Rev 3 ...
Page 8: ...vi C12 Rev 3 ...
Page 14: ...Table of Contents xii C12 Rev 3 ...
Page 16: ......
Page 30: ...Setup Operation 2 Specifications 16 C12 Rev 3 2 4 Outer Dimensions Unit mm ...
Page 84: ......
Page 155: ...Maintenance 4 Cable Unit C12 Rev 3 141 4 2 Connector Pin Assignment 4 2 1 Signal Cable ...
Page 156: ...Maintenance 4 Cable Unit 142 C12 Rev 3 ...
Page 157: ...Maintenance 4 Cable Unit C12 Rev 3 143 ...
Page 158: ...Maintenance 4 Cable Unit 144 C12 Rev 3 4 2 2 Power Cable ...