EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
©
Ericsson AB 2010
Commercial in confidence
147 (200)
8
EDA 2530 Equipment Test and Alarm Checks
8.1
Equipment Test
This subsection describes the actions to be carried out to test the EDA 2530
equipment before it is connected to a network.
8.1.1
Optical Launch Power Test
This measurement should be taken at the optical distribution frame (ODF) if present,
but if not directly at the card optical transmitter output.
a.
Disconnect the Transmit optical fibre(s) of the unit being tested, then use an
optical power meter to measure the Transmit Launch Power from each port
of the unit under test.
b.
Check that the measurement is within limits, as specified in the TX Launch
Power Limits table below.
TX LAUNCH POWER LIMITS
OPTICAL
MODULE
INTERFACE
MAX LIMIT
MIN LIMIT
SFP-SU57AD 1000BASE-SX GbE, 850nm,
Multi-Mode, >2Km
-3.5
dBm
0.44668
mW
-9.5
dBm
0.11220
mW
SFP-SU57AE 1000BASE-LX
GbE,
1310nm,
Single-Mode, 10Km
-3.0
dBm
0.50118
mW
-9.5
dBm
0.11220
mW
SFP-SU57AJ 1000BASE-EX GbE, 1310nm,
Single-Mode, 40Km
0 dBm
1 mW
-4.5
dBm
0.35481
mW
SFP-SU57AF 1000BASE-ZX
GbE,
1550nm,
Single-Mode, 70Km
+5.0
dBm
3.16227
mW
0 dBm
1 mW
8.1.2
Unit Status Check
Check that the LCT screen display corresponds to the real status of the equipment.
i.e. that all the electronic units present in the equipment are properly displayed, and
that there are no inconsistencies between the actual status and the displayed one,
both for the alarms and the functional status of the units.
Right click on each unit and select
“Show Actual”
, then “Actual Card is ………..”