EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
©
Ericsson AB 2010
Commercial in confidence
7 (200)
1
Introduction
1.1
Objective
The objective of this document is to detail the procedures for commissioning of the
EDA 2530 when used in the Cable and Wireless Access network.
1.2
Scope
This document will be used to commission the EDA 2530 DLE Node on site.
The DLE IP DSLAM EDA 2530
(EDA 0x0x)
shelf can be equipped with up to ten 64
x ADSL2+ Cards and ten 64 x POTS/VoIP Cards and up to four 32 x SHDSL Cards
as required. The 64 x POTS/VoIP Card will be configured for H.248 protocol. The
ADSL2+, POTS/VoIP Cards and 32 x SHDSL Cards VLANs will be routed to the
GigaBit Ethernet Port of the EDA 2530 CP-IP Card. The Common Part “Backhaul”
GigaBit Ethernet Port will be connected to the IP network.
The tests in the document are to prove the functionality of the EDA 2530. These
tests will include the set-up and connection of the Local Controller, the loading of
site specific Database and the setting up of circuits through the EDA 2530.
Engineers MUST familiarise themselves with the procedure and be aware of and
observe all safety precautions BEFORE starting the commissioning procedure.
1.3
Safety Procedures
All procedures should be carried out in accordance with the Safety Rules and Safety
Notices as stated in the product handbook.