EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
©
Ericsson AB 2010
Commercial in confidence
9 (200)
1.8
Required Information For Commissioning
The Customer Network Planning Authority shall be responsible for providing the
following information before commissioning can commence.
a.
Unit type and location of cards in the subrack.
b.
IP over Ethernet Addresses of each EDA 2530 (DLE Node Address).
c.
Site/slot specific IP addresses for POTS cards.
d.
IP address of the NTP Server.
e.
If available, fibre loss figures for the sub-network under test.
f.
The SID document, which specifies Configuration information i.e. Site
location, Floor Plan, Rack Layout, Fuse allocations, MDF block locations for
the EDA 2530 Subrack equipment, and Cable Running Out Lists.
g.
Alarm Profile list for each unit type that is to be commissioned in the
subrack.
1.9
Documentation Change Request
In order to allow changes to this document to be implemented quickly, site
engineers are requested to use the Document Change Request Form at the end of
this document. The form should be sent by post, fax or e-mail to the author of this
document for the change request to be considered.
End of section